  • 22 March 2019 | Final round!

    22 March 2019 | Final round!

    Almost completetd. Most of the painting work has been done and the ceiling panels and lighting in the ceilings are being installed. Needle felt rugs and vinyl flooring are laid in the offices and baseboards are installed. At the moment, the screed is still drying in the last section of the ground floor so that the last covering floor can be laid as well.
    Also, the tiling in the sanitary rooms and toilets are finished. Now the plumber and the carpenter take up their work and rooms will be finished.
    In the outdoor area, a rhombus wood cladding was installed. Both in the area of the main entrance and in the terrace area of the lounge, before it continues with the plaster work in the outdoor area next week.

    Final round Berner Terass construction site Berner
    Rooms construction site Berner
  • 17 January 2019 | News from the construction site

    17 January 2019 | News from the construction site

    In the last weeks of the year, the underfloor heating system was installed in the hall floor and the hall siding was concreted, the roof seal of the office building made, and the timber frame construction mounted and the drywalls installed in the office. With the beginning of the drywalls, things also continued right at the beginning of the year and the electrical system and sanitary facilities on the first floor were already installed and kilometers of cable laid. Outside, the dirt and rainwater pipes were made.

    Baufortschritt Berner Baustelle Berner
    Baustelle Berner
  • 12 December 2018 | Construction progress

    12 December 2018 | Construction progress

    The shell is almost closed. Among other things, the hall roof has been sealed in recent weeks and the first windows have been installed and additional wall panels have been installed on the façade.
    But the interior of the building is also progressing. The fine planum was produced in the hall and the insulation was installed to prepare the hall floor. In the office wing, the timber frame construction was prepared and assembled for the individual.

    Construction progress Berner Construction progress Berner
    Construction progress Berner Construction progress Berner
  • 8 November 2018 |  On the construction site, things are progressing well!

    8 November 2018 | On the construction site, things are progressing well!

    You can almost watch as our new office and hall building grows. In the last few weeks, a lot has happened on the construction site. For example, the staircases including the platforms, walls and ceilings were installed in the staircases. The concrete work of the hall and office ceiling was carried out, the wall panels for the hall body were delivered and installed, and glulam beams and the roof trapezoidal sheets were delivered and installed. First steps into the new building make clear how generous and spacious the new premises will be.

  • 21 September 2018 | The first supports were provided.

    21 September 2018 | The first supports were provided.

    The final planning and preparations of the individual trades, which are involved in the interior design, run in the background. But on the construction site, the construction progresses and grows upwards. The first precast columns have already been set and you can get a rough idea about the design.

  • 10 August 2018 | Earthworks began

    10 August 2018 | Earthworks began

    In addition to the creation of a construction site entrance and the construction road, a webcam was installed, where you can follow the action on the construction site at any time. Topsoil was removed, fill sand supplied, introduced and compacted, and the reinforcement delivered and installed.

  • 5 July 2018 | Groundbreaking

    5 July 2018 | Groundbreaking

    In the presence of all employees and some invited guests, the ground-breaking ceremony for our new building on Werner-von-Siemens-Straße in Elmshorn took place on 5 July18.

    At this point, we give you with our construction diary a little insight into the ongoing construction.